Wairakei Power Station, Taupo.

Nga Awa Purua Geothermal Power Station, Taupo.

W - Line 900NB Pipeline

Date: 2012

Client: Contact Energy

Location: Wairakei Power Station, Taupo.

Length: 1.3 km

Size: 900NB

Fast facts:

  • The W-Line is a 900Nb pipeline located at the Contact energy Wairakei Power Station, Taupo.

  • A new 900NB reinjection pipeline was required to transport the additional reinjection water produced by the new Te-Mihi Power Station to the Otupu reinjection wells located beside the main Taupo bypass highway.

  • The pipeline followed a difficult route between the side of the highway and Prawn Park, over a creek and through several culverts including a culvert under the main highway.

  • Warner Construction completed W-Line pipeline on time, to budget with no quality issues and with an excellent safety record of no incidents.

Fabrication and Installation carried out by Warner Construction:

  • Wellhead thrust frame

  • Wellhead and valve access platforms

  • Silencer

RK36 Production Wellhead Hookup

Date: 2017

Client: Mercury Energy

Location: Nga Awa Purua Geothermal Power Station, Taupo.

Length: 145m

Size: 350NB and 450NB pipe

Fast facts:

  • A new production well was commissioned by Mercury Energy alongside the exisiting RK13 and RK5 wells.

  • Warner Construction connected the well to the exisiting H-Line running back to the Nga Awa Purua Geothermal Power Station.

Fabrication and Installation carried out by Warner Construction:

  • Wellhead thrust frame

  • Wellhead and valve access platforms

  • Silencer