Te Huka Steamfield, Taupo
The Te Huka Unit 3 will be an additional unit at the existing Te Huka geothermal power station located in Taupo, New Zealand.
The plant is incorporating a novel design that will enable the carbon emissions from the project to be reinjected into the reservoir in the future. Continuing with their current works in the vicinity for Contact Energy, Warner Construction was ready to start this assignment immediately after finishing the Tauhara Steamfield project.
Te Huka Steamfield, Taupo
Date: 2023 - Due completion Sept 2024
Client: Contact Energy
Length: 5kms (approx)
Size: 500NB & 750NB
Fast facts: Te Huka Unit 3 Upgrade works
1 x Reinjection line
1 x Production line
1 x Separator Station
1 x Venting Station
1 x SGW Drum
1 x Rock Muffler
Both of Warner Constructions' workshops in New Plymouth and Taupo were used for pipeline and ancillary works for the project.