Ohanga Rd Pipeline, New Plymouth
Warner Construction strengthens its long-term partnership with Greymouth Petroleum, selected again as a preferred supplier for pipeline works due to their proven track record and ongoing positive working relationship.
The new pipeline installation from the Urenui well site to the Turangi production station was carried out over 5 months.
Ohanga Rd Pipeline
Date: 2024
Client: Greymouth Petroleum
Length: 4.5kms
Size: 4 inch pipe
Fast facts:
New pipeline required from the Urenui A Well site to Turangi A meeting/production station
Roadside traffic management provided by Warner Construction
Weld out pipe, 100% NDT tested, blast and wrap followed by jeeping for longevity testing before underground placement.