Henderson Compressor Station, Auckland.

This project is a prime example for showcasing Warner Constructions’ capabilities to undertake and execute multi-discipline civil and mechanical contracts in-house.

Warner’s has the inventory to carry out projects from conceptual to installation. Their skillset and proven track record have been refined to a very high standard with decades of engineering expertise and knowledge.

Being commissioned as the one-stop option for this project enabled Warner to simultaneously and independently carry out all civil and mechanical works over a 6 month period. WCL also provided support during station start up. This company has the resources and agility to locate anywhere in New Zealand.

Client: First Gas Ltd

Date: 2016/2017

Location: 110 Amreins Road, Taupaki, Henderson, Auckland.

Time frame: 6 months

Civil Package:

Cut and metalled site access driveway

Foundations surveyed and formwork for 2 x 30-Ton compressors

Control room and utilities buildings

Transformer Pad

Air Compressor Building

Workshop, store, lunchroom and bathroom facilities

Concrete foundations for miscellaneous structures

Ancillary buildings

Earthworks, stormwater, vegetated swales and landscape planting

Construction of timber retaining walls

Compressor House Foundations:

Very complex series of embedded hold-down bolts

A high degree of accuracy required to fit compressor base frames

30-Ton compressors installed on foundations and covered for weather protection

Compressor House Building:

Erection of steel framework

All steelwork fabricated, transported and erected by Warner Construction

Gantry crane installed

Mechanical Package:

Installation of two new electrically driven reciprocating compressor packages at Henderson Compressor station.

Works included fabrication & site installation of pipework, pipe supports, coalescer vessel, filter skids, oil coolers, lube oil pumps, tanks, silencer tanks, instrument air system, stairs, platforms access ways.

Onsite welding and painting.

Pipe spools were fabricated, hydro-tested and painted at the WCL Waitara branch, then transported to site and installed.

Provided commissioning support upon station start-up.

Previous
Previous

Bell Block, New Plymouth